MS Project Link Type

 May 19, 2018     Introduction to MS Project, MS Project Certification in Lahore, MS project online Training in Pakistan, MS Project Training in Lahore     No comments   

How do Task Links affect the Schedule?

Task Links Show the Relationship in time of one task to another. Linking Tasks Create task dependencies. The long Chain of Tasks determine the entire length and end of a project.

Link Type
FINISH TO START  ( FS)
START TO START (SS)
FINISH TO FINISH (FF)
START TO FINISH  (SF)

1)
Finish to Start    (FS)
Suppose A, and B  are two task the Task B depends on Task A .
The Task B can not Start until the Task A is Complete.

2)
START TO START   (SS)
 Suppose A and B  are two Task and B Depend on task A . The Task B cannot begin until the task that it depend on A Begin.
The Dependent task  B can b Start any time if the task a is start . Start to start link does not require the both task begin at same time.
3)
Finish To  Finish    (FF)
Suppose A and B are Two Task and B depend on Task A .The dependent Task B can not finish  until the task A is  not finished.
4)
Start TO Finish     (SF)
The Dependent task B cannot be Completed until the task that is depends on A begins.
For more details about Microsoft project training and MS Project 2016  training please visit :



http://asipt.net/ms-project-management/


Read More
  • Share This:  
  •  Facebook
  •  Twitter
  •  Google+
  •  Stumble
  •  Digg

Introduction to Base line

 May 19, 2018     MS Project 2016 Training in lahore, MS Project Certification in Lahore, MS Project Certification in Pakistan, MS project online Training in Pakistan, What is Baselines     1 comment   

Baselines
A baseline is a group of nearly 20 primary reference points (in five categories: start dates, finish dates, duration, work, and cost estimates) that you can set to record the original project plan when that plan is completed and refined. As the project progresses, you can set additional baselines (to a total of 11 for each project) to help measure changes in the plan. For example, if your project has several phases, you can save a separate baseline at the end of each phase, to compare planned values against actual data.

For More details about project management please visit: http://asipt.net/ms-project-management/ 
How to Create a Baseline
Go to the the Projects
you can See two Options
Set Baseline
Clear Baseline
Click the Set Baseline

For more details about Microsoft project training and MS Project 2016  training please visit :
http://asipt.net/ms-project-management/
Read More
  • Share This:  
  •  Facebook
  •  Twitter
  •  Google+
  •  Stumble
  •  Digg

How to Create Report in MS Project

 May 19, 2018     Introduction to MS Project. MS Project Online Training, MS Project 2016 Training in Lahore., MS Project Training in pakistan     No comments   

1
Reports
You can Generate Multi-pal reports   in MS Project Like Costs , dashboards, Report in Progress, Also New Report.
For this purpose go to the Reports option and below yo can see all different option related to reports. select one of them.
 Here i Select Costs 
For More details about project management please visit: http://asipt.net/ms-project-management/ 
  
This Report show Cash Flow, Cost Overruns, Earned Value Report, Resource Cost.
2.
In Progress Report
Go to the Report and select the In Progress Report
in Progress Report  show Critical Tasks, Late Tasks, Milestone Report, Slipping Report.
 3.
For the all report template click the Report and select the New Report,
this report template show Blank , Chart , Table , Comparison,

For more details about Microsoft project training and MS Project 2016  training please visit :
http://asipt.net/ms-project-management/


Read More
  • Share This:  
  •  Facebook
  •  Twitter
  •  Google+
  •  Stumble
  •  Digg

Thursday, 17 May 2018

Link Task In MS Project

 May 17, 2018     MS Project, MS Project Certification in Pakistan, MS Project course outline, MS project online Training in Pakistan, MS Project Training in Lahore     No comments   

How to link Task in MS Project 

Select Task to link
1)
Link Between Tasks show dependencies mean which task are interlinked with  each other or  depend on another , So for this Purpose Click the Task tab in the menu bar.

2)
Select the Desire two task that you want to link.
After the Selection of two  task click the chain icon in the ribbon to link the task.
yow will see and arrow appear in the Gantt Chart that connects the Two tasks.
For More details about project management please visit: http://asipt.net/ms-project-management/ 
For more details about Microsoft project training and MS Project 2016  training please visit :
http://asipt.net/ms-project-management/
Read More
  • Share This:  
  •  Facebook
  •  Twitter
  •  Google+
  •  Stumble
  •  Digg

How to add Task in MS Project

 May 17, 2018     MS certification in Pakistan, MS Project Online Training in Lahore, MS project online Training in Pakistan, What is Task     No comments   

How to create a new Task
1)
Go to the List of Projects and Select the Desire Project in which you want to create a  task.
Click the Desire Projects and open it.
2)
On the Task Tab Click the edit.
You can see a screen which have column Task name, Duration, Start date, Finish Date.
3)
Click the Cell  and  assign task name at here 
Duration, start and finish date is automatically generated but you can edit according to your project schedule.  
              For more Details about MS project Management  Please Visit http://asipt.net/ms-project-management/


For more details about Microsoft project training and MS Project 2016  training please visit :
http://asipt.net/ms-project-management/


Read More
  • Share This:  
  •  Facebook
  •  Twitter
  •  Google+
  •  Stumble
  •  Digg

Wednesday, 16 May 2018

How to Create a Calendar in MS Project

 May 16, 2018     MS Project Certification in Pakistan, MS project online Training in Pakistan, MS Project Training in Lahore     No comments   

1.Create a New Base Calendar
 Add new Base Calendar in Ms Project go to the Project option and  click the Change Working Time.

 For More details about project management please visit: http://asipt.net/ms-project-management/ 

2.
Yo can See a new Screen on a window click the Create New Calendar.

For More details about project management please visit: http://asipt.net/ms-project-management/ 
3.
Assign a calendar name in a name Field and  Select a Create new Base Calendar and then Press Ok.

4.
You Can See Two Option Work Weeks and Exception   Work week Indicate the Whole Working Day of Your Schedule and the Exception show the holidays to your Schedule.
Click The Work weeks and go to the Details option.

For More details about project management please visit: http://asipt.net/ms-project-management/ 

In Details You can See Three Different option
Use Project Default Time For these Days.
Set Days To nonworking Time.
Set Days to these Specific Working Time.
you can add specifically Information working or nonworking days by clicking on as a individual Option according to your requirement.

7.
Finally Click on OK.
Then Return to the change working time dialog box and then click OK again.

For more details about Microsoft project training and MS Project 2016  training please visit :
http://asipt.net/ms-project-management/

Read More
  • Share This:  
  •  Facebook
  •  Twitter
  •  Google+
  •  Stumble
  •  Digg

Tuesday, 15 May 2018

How to Create a Task List In MS Project

 May 15, 2018     MS Project Certification in Pakistan, MS project online Training in Pakistan, MS Project Training Academy in Lahore, Task list in MS Project     No comments   

Define project tasks 

 A project is a Collection of tasks. Each task represents   Specific piece of work that must be done to complete the project.

Task
Task is a Piece of work to be done or undertaken.

  1. Creating a Task List.
Open Microsoft Project then click the Blank Project , then Assign a Proper Task name in the Task Name Column.
When You Assign Task name , The System Gen rate Start and Finish Date  Automatically You can edit This data By Clicking on a Field, and Assign Proper Start and Finish data according to Your Project Requirement. 

/http://asipt.net/ms-project-management/

Go to the view tab and Click the Timeline Bar that display the above of the Task list then select the any Task that are mentioned in Task list and Right Click on the task and Choose the Add Timeline in the list and Click It.


3) 
if you want to add multi pal  task to timeline then Select the  the Whole Task and Right Click and choose the add timeline , in this case your multi pal task is added to the list timeline at once time. 

For more details about Microsoft project training and MS Project 2016  training please visit :
 http://asipt.net/ms-project-management/
Read More
  • Share This:  
  •  Facebook
  •  Twitter
  •  Google+
  •  Stumble
  •  Digg
Older Posts Home

Popular Posts

  • Link Task In MS Project
    How to link Task in MS Project  Select Task to link 1) Link Between Tasks show dependencies mean which task are interlinked with  each o...
  • How to Create a Task List In MS Project
    Define project tasks   A project is a Collection of tasks. Each task represents    Specific  piece of work that must be done to complete t...
  • MS Project Introduction
    Introduction Microsoft Project is aproject management software program developed and sold by Microsoft, designed to assist a project ma...

Recent Posts

Categories

  • Developing the Product
  • Introduction Of Microsoft Project
  • Introduction to MS Project
  • Introduction to MS Project. MS Project Online Training
  • List of Mmicrosoft Project Module
  • Marketing
  • Microsoft Project Course Content
  • MIcrosoft Project Course Outline
  • MS certification in Pakistan
  • MS Component
  • MS Project
  • MS Project Certification in Pakistan
  • MS Project 2016
  • MS Project 2016 Training in lahore
  • MS Project 2016 Training in Lahore.
  • MS Project certification
  • MS Project Certification in Lahore
  • MS Project Certification in Pakistan
  • MS Project course outline
  • MS Project online training
  • MS Project Online Training in Lahore
  • MS project online Training in Pakistan
  • MS project Prectical Training
  • MS Project Training Academy in Lahore
  • MS Project Training in Lahore
  • MS Project Training in pakistan
  • People Role..
  • Stratgic Planning
  • Support
  • Task list in MS Project
  • What is Baselines
  • What is Resource
  • What is Task

Unordered List

Pages

  • Home

Text Widget

Blog Archive

  • May 2018 (8)
  • April 2018 (3)

Search This Blog

Powered by Blogger.

Report Abuse

About Me

Unknown
View my complete profile

MS Project Link Type

How do Task Links affect the Schedule? Task Links Show the Relationship in time of one task to another. Linking Tasks Create task depend...