How do Task Links affect the Schedule?
Task Links Show the Relationship in time of one task to another. Linking Tasks Create task dependencies. The long Chain of Tasks determine the entire length and end of a project.
Link Type
FINISH TO START ( FS)
START TO START (SS)
FINISH TO FINISH (FF)
START TO FINISH (SF)
1)
Finish to Start (FS)
Suppose A, and B are two task the Task B depends on Task A .
The Task B can not Start until the Task A is Complete.
2)
START TO START (SS)
Suppose A and B are two Task and B Depend on task A . The Task B cannot begin until the task that it depend on A Begin.
The Dependent task B can b Start any time if the task a is start . Start to start link does not require the both task begin at same time.
3)
Finish To Finish (FF)
Suppose A and B are Two Task and B depend on Task A .The dependent Task B can not finish until the task A is not finished.
4)
Start TO Finish (SF)
The Dependent task B cannot be Completed until the task that is depends on A begins.
For more details about Microsoft project training and MS Project 2016 training please visit :
http://asipt.net/ms-project-management/
For more details about Microsoft project training and MS Project 2016 training please visit :
http://asipt.net/ms-project-management/
0 comments:
Post a Comment